§ 20-101. Definitions  


Latest version.



  •    (a) In general. -- In this subtitle the following words have the meanings indicated.

    ** REVISOR'S NOTE
     
       This subsection formerly was Art. 29, § 3-102(a)(1).

    ** REVISOR'S NOTE
     
       The only change is in style.

    (b) Design/build contract. -- "Design/build contract" means a contract that provides for both architectural and engineering design services and construction services as a part of a single contract.

    ** REVISOR'S NOTE
     
       This subsection formerly was Art. 29, § 3-102(a)(2).

    ** REVISOR'S NOTE
     
       No changes are made.

    (c) Evaluated bid price. -- "Evaluated bid price" means the price of a bid after adjustment in accordance with objective measurable criteria.

    ** REVISOR'S NOTE
     
       This subsection is new language derived without substantive change from former Art. 29, § 3-102(d)(1)(i) and (ii).

    ** REVISOR'S NOTE
     
       The former reference to the defined term applying to "this subsection" is deleted in light of the reorganization of former Art. 29, § 3-102(d) in this subtitle.

    ** DEFINED TERM:
     

       "Objective measurable criteria"                                     § 20-101

    **

    (d) Facilities construction contract. -- "Facilities construction contract" means a contract that provides services for the construction of: **

       (1) a water or wastewater treatment plant; **

       (2) a water or wastewater pumping station and related force mains in the pumping station site limits; **

       (3) a water storage facility; **

       (4) a wastewater storage facility; **

       (5) a building for Commission purposes; or **

       (6) a pipeline.

    REVISOR'S NOTE
     
       This subsection is new language derived without substantive change from former Art. 29, § 3-102(a)(3).

    REVISOR'S NOTE
     
       In item (4) of this subsection, the word "or" is substituted for the former word "and" for clarity.

    REVISOR'S NOTE
     
       In item (5) of this subsection, the reference to "a building for Commission purposes" is substituted for the former reference to "building[s]" for clarity.

    REVISOR'S NOTE
     
       The Washington Suburban Sanitary Commission Law Review Committee notes, for consideration by the General Assembly, that the reference to "buildings" in former Art. 29, § 3-102(a)(3)(iv) is unclear. The Committee has interpreted the reference to mean any building for Commission purposes. This substitution is called to the attention of the General Assembly.

    "Commission"                                                           § 16-101

    **

    (e) Objective measurable criteria. -- "Objective measurable criteria" means standards that enable the Commission to compare the economy, effectiveness, or value of the subject of the bids.

    REVISOR'S NOTE
     
       This subsection formerly was Art. 29, § 3-102(d)(1)(iii).

    REVISOR'S NOTE
     
       The only change is in style.

    "Commission"                                                           § 16-101



HISTORY: An. Code 1957, art. 29, § 3-102(a)(1)-(3), (d)(1)(i)-(iii); 2010, ch. 37, § 3; 2012, ch. 140.