§ 12-605. Electrical inspection certificates  


Latest version.



  •    (a) Before authorizing electrical current to be turned on. -- Before a utility authorizes electrical current to be turned on for a premise or structure, the utility must receive a cut-in certificate from a certified nongovernmental electrical inspector or governmental unit that is qualified to issue electrical inspection certificates.

    (b) After completion of electrical installation. -- Within 15 days after completion, each electrical installation shall be certified by a certified nongovernmental electrical inspector or a governmental unit that is qualified to issue electrical inspection certificates.


HISTORY: 2010, ch. 127.