§ 25-702. Approval.  


Latest version.



  •    (a) Required submissions. -- Before the county enters into any contract or agreement with the United States and before any plan relating to a flood control or navigation project or the maintenance or operation of a flood control or navigation project is approved, the county shall submit for consideration each contract, agreement, or plan affecting a State road or land in a park or parkway under the jurisdiction of the Commission to:

       (1) the State Highway Administration; and

       (2) the Commission.

    (b) Limitation. -- The county may not approve a plan or enter into a contract or an agreement that is inconsistent with:

       (1) the purposes of the Capper-Cramton Act, Public Law 71-284, 46 Stat. 482; or

       (2) any agreement between the Commission and the National Capital Planning Commission related to the park and parkway system authorized by that Act.


HISTORY: An. Code 1957, art. 28, § 9-101(a)(2), (b); 2012, ch. 426, § 2.