§ 25-210. Site plan review -- District council.  


Latest version.



  •    (a) Authorized; appeal. --

       (1) Subject to subsection (b) of this section, the district council may review a final decision of the county planning board to approve or disapprove a detailed site plan.

       (2) A party of record may appeal to the district council a final decision by the county planning board to approve or disapprove a site plan.

    (b) Initial consideration. -- The district council may only decide whether to review the final approval or disapproval of a detailed site plan under this section within 30 days after the date the final approval or disapproval was issued.

    (c) Hearing. --

       (1) Except as provided in paragraph (2) of this subsection, if the district council decides to review an approval or a disapproval under this section, the district council shall hold a hearing within 70 days after the district council issues the decision to conduct a review.

       (2) The district council may decide to extend the time to hold a hearing under paragraph (1) of this subsection for up to 45 additional days on its own motion or on request of the applicant.

    (d) Final decision. -- The district council shall issue a final decision within 60 days after the date of the hearing.

    (e) Revocation of delegation. -- The district council may revoke a delegation of site plan approval authority to the county planning board only for the purpose of delegating approval authority over detailed site plans to the governing body of a municipal corporation in the regional district under § 25-301(c)(2)(ix) of this title.


HISTORY: An. Code 1957, art. 28, § 8-129; 2012, ch. 426, § 2.